Welcome to the future home of Minnesota Rural Electric Association

BUILDING DETAILS

  • Cost: $4.3 million
  • Size: 12,000 square feet
  • Main floor events center with capacity for hosting up to 60 participants
  • Modern event and office space designed to enhance the productivity of our building and our team

Building for Our Members, Growing for the Future

As we’ve grown and evolved to meet the needs of our member cooperatives, so have the demands on our space. That’s why we’re taking the exciting step of constructing a new headquarters at our current site, designed to support our members and our mission for decades to come.

Building for Our Members,
Growing for the Future

As we’ve grown and evolved to meet the needs of our member cooperatives, so have the demands on our space. That’s why we’re taking the exciting step of constructing a new headquarters at our current site, designed to support our members and our mission for decades to come.

Why Build a New Headquarters?

Our decision wasn’t made lightly. For years, we carefully explored every option — upgrading, remodeling or building new. In the end, building a new facility on our current site proved to be the most financially sound and sustainable choice for our members. Here’s why:

A Thoughtful Process
We’ve taken the time to evaluate what’s best for our members and staff, ensuring this project is a smart and necessary investment.

Outdated Space
Our current building requires significant costly upgrades, but its design can no longer accommodate our needs.

Space to Grow
We’re planning for the future by creating a space that supports growth, collaboration and innovation.

Convenient Location
Staying on the current site, served by Wright-Hennepin Electric Cooperative, ensures we remain accessible to members while being close to local amenities like hotels, restaurants and businesses.

 

What Will the New Facility Offer?

The new headquarters is designed to improve how we serve our members:

Modern Meeting Space
A state-of-the-art meeting room that seats up to 60 people, allowing us to host more events onsite and reduce rental costs.

Efficient Design
A layout that maximizes office space and parking while making better use of our land.

Built for the Future
This building will service our members for decades to come, designed with adaptability and long-term goals in mind.

Stay Connected with the Project

We’re excited to share updates with our members as the project progresses. From groundbreaking to completion, we’ll keep you informed every step of the way. Together, we’re building a brighter future for MREA and the cooperatives we serve.

During Construction

During construction, MREA will lease office space where employees can collaborate and prepare materials for upcoming events. Employees will regularly work from home except for time each week when departments will meet at the leased office space. The location of the leased space has not yet been finalized.

Stay Connected with the Project

We’re excited to share updates with our members as the project progresses. From groundbreaking to completion, we’ll keep you informed every step of the way. Together, we’re building a brighter future for MREA and the cooperatives we serve.

During Construction

During construction, MREA will lease office space where employees can collaborate and prepare materials for upcoming events. Employees will regularly work from home except for time each week when departments will meet at the leased office space. The location of the leased space has not yet been finalized.

                                                         Project Timeline

2022-2023
Ongoing discussion and analysis about current facility maintenance expenses, remodeling, leasing or building a new facility.
2024
April
Board’s initial decision to move forward with a building
June
Decision to build on current location
September
Maple Grove Planning Commission and City Board approval
December
Final MREA board decision on building project
2025
March
Move out of current building and demolition
April
Excavation and site preparation
May
Exterior Construction
October
Interior Construction
2026
April
Move In